Electricity Department, How it started.
Historical Background:
The commissioning of the two sets of hydro
electric generators having capacities of 100 KW and
56 KW at Leimakhong micro hydel station in 1930 by the
then Manipur State Hydro Electric Board marked
the beginning of the use of electricity in Manipur.
The Royal palace and the main area of Imphal Town
enjoyed Electricity generated from this captive hydel
station. During the Second World War, two more Diesel
Generating sets of 62 KW and 46 KW capacities were
installed at the old Imphal Power House by the Armed
Forces for electrification of Imphal and its suburbs.
The capacity remained the same without further capacity
addition till the end of the first Five Year plan
(1951-56) of the post independence period.
The second Five Year Plan (1956-61) however
saw a significant change in the demand of power in the
state. The demand had been growing rapidly due to
social acceptance and the gradual wareness of the
people towards the use of electrical power for
different purposes. This had necessitated further
addition in the generation capacity and it was
accomplished with the installation of more DG sets of
various capacities in and around Imphal.
To evacuate the power generated from the captive mini
hydel power station (100 + 56) KW at Leimakhong to
specific load centres of Palace Compound and main
bazar of Imphal, a 20 Km. long 11 KV line between
Imphal & Leimakhong was constructed for the first
time in Manipur in 1930. The state was then having 26
Kms. of 11 KV line and 45 Kms. of domestic lines to
serve a few consumers in 7 villages/Leikais.
Both the line and generating stations were owned by
the then Manipur State HE Board, constituted under
the ex-officio Chairmanship of the then Political
Agent. Subsequently Electricity was kept under the
administrative control of the Public Works Department
(PWD), Government of Manipur. It was later separated
from PWD and started functioning as an independent
department w.e.f. February, 1970.
The peak load demand of Manipur in 1971 was 3.6 MW only. The
demand was met from the State's own generating
stations and power purchased from the neighbouring
states/Electricity Board at low voltage. The per
capita consumption of energy was 4.84 KWH. The demand
was kept suppressed due to lack of Generation till the
year 1980. The scenario abruptly changed after the
purchase of bulk power from Assam with the
commissioning of 132 KV inter-state transmission line
from Imphal to Dimapur and with the commissioning of a
6.3 MVA, 132/33 KV sub-station at Yurembam in December
1981. The situation was further alleviated with the
commissioning of Loktak Project having a capacity
of 3x35 MW on 4th of August, 1984.
|