As the state's major consumer is in the domestic sector, there is an acute shortage of power during the evening peak load hours. This has necessitated the department to resort to wide spread load shedding through out the state round the year.

The Load Shedding programme currently in force in the state with effect from 1st December, 2003 is as follows :  
 
Load Shedding programme
4.30 pm to 9.00 pm
 
Group Sl. No. Name of feeder Name of Sub-Station Dates of shedding
A. 1. 11 KV DMC 33/11 KV Khuman Lampak 1st, 4th, 7th, 10th, 13th December, 03
and so on.
2. 11 KV Tiddim - I 132/33/11 KV Yurembam
3. 11 KV Canchipur 33/11 KV Mongsangei
4. 11 KV Mantripukhri 33/11 KV Khuman Lampak
5. 11 KV Minuthong 33/11 KV Khuman Lampak
6. 11 KV Wangkhei 33/11 KV Kongba
7. 11 KV Tiddim 33/11 KV Keisampat
A1 1. 11 KV Singda 33/11 KV Iroisemba 1st, 4th, 7th, 10th, 13th December, 03
and so on.
2. All 11 KV (except Army) 33/11 KV Leimakhong
3. All 11 KV feeders 33/11 KV Nilkuthi
4. 11 KV IB 132/33/11 KV Churachandpur
5. 11 KV Singhat 132/33/11 KV Churachandpur
6. All 11 KV feeders 132/33/11 KV Kakching
7. 11 KV Yairipok 33/11 KV Kongba
8. 11 KV Yaingangpokpi 132/33/11 KV Yaingangpokpi
9. All 11 KV feeders 33/11 KV Utlou
B 1. 11 KV Western 132/33/11 KV Yurembam 2nd, 5th, 8th, 11th, 14th December, 03
and so on.
2. 11 KV Heirangoithong 33/11 KV Mongsangei
3. 11 KV DC 33/11 KV Iroisemba
4. 11 KV TV 33/11 KV Khuman Lampak
5. 11 KV Bazar 33/11 KV Keisampat
6. 11 KV University 33/11 KV Mongsangei
7. 11 KV Khongman 33/11 KV Kongba
8. 11 KV Nityainanda 33/11 KV Lamphel
9. 11 KV Lamlong 33/11 KV Khuman Lampak
B1 1. 33 KV New Chayang 132/33/11 KV Kakching 2nd, 5th, 8th, 11th, 14th December, 03
and so on.
2. All 11 KV (except AIR) 33/11 KV Mayang Imphal
3. All 11 KV feeders 33/11 KV Wangjing
4. All 11 KV feeders 33/11 KV Thoubal
5. 11 KV Bishnupur 132/33/11 KV Ningthoukhong
6. 11 KV Khangvai 132/33/11 KV Churachandpur
7. 11 KV Khenjang 132/33/11 KV Churachandpur
8. 11 KV Tadubi 132/33/11 KV Karong
C 1. 11 KV Eastern - I 132/33/11 KV Yurembam 3rd, 6th, 9th, 12th, 15th December, 03
and so on.
2. 11 KV CRPF 132/33/11 KV Yurembam
3. 11 KV Hiyangthang 33/11 KV Mongsangei
4. 11 KV Lamphel 33/11 KV Lamphel
5. 11 KV Uripok 33/11 KV Lamphel
6. 11 KV Langol 33/11 KV Iroisemba
7. 11 KV Thambalkhong 33/11 KV Kongba
8. 11 KV Eastern - II 33/11 KV Keisampat
9. 11 KV Nambul Mapal - I 33/11 KV Mongsangei
10. 11 KV Nambul Mapal - II 33/11 KV Keisampat
C1 1. 11 KV Litan 132/33/11 KV Yaingangpokpi 3rd, 6th, 9th, 12th, 15th December, 03
and so on.
2. 11 KV Nambol 33/11 KV Bishnupur
3. All 11 KV feeders 33/11 KV Napetpalli / Lamlai
4. All 11 KV feeders 33/11 KV Moirang
5. All 11 KV feeders 33/11 KV Moirang Khunou
6. 33 KV Tengnoupal 132/33/11 KV Kakching
7. All 11 KV feeders 132/33/11 KV Karong
8. 33 KV Kangpokpi 132/33/11 KV Karong
9. 11 KV Ningthoukhong 132/33/11 KV Ningthoukhong
 
 
 
From 12.00 pm (midnight) to 5.00 am of next morning
 
Sl. No. Feeders Dates of shedding
1. Feeders at Group A1, B1, C1 Daily
2. Feeders at Group A & C 2nd, 4th, 6th, 8th December, 2003
and so on
3. Feeders at Group B 1st, 3rd, 5th, 7th December, 2003
and so on

Besides the above load-shedding programme, there may be further shedding on receipt of instruction from NERLDC, Shillong to maintain grid discipline, as and when required.