System Improvement
System Improvement Schemes :
The department has been taking up system
improvement schemes for the last decade so as to reduce
the system losses besides augmenting the distribution
capacity of the department. Each year varoius 11 KV
lines section are upgraded by replacement of small
conductors by higher current carrying capacity
conductors. New 11 KV lines are erected to augment
the old ones. Similarly small 11/0.4 KV distribution
sub-stations which are nearly fully loaded are upgraded
by transformers of higher ratings. New distribution
sub-stations are installed at vrious load centres to
reduce the loading of the nearby older distribution
sub-stations.
On the LT lines side also, small size LT conductor are
being replaced by higher current carring capacity LT
conductors. More LT lines are strung where ever
necessary to reduce overloading of the existing LT
conductors.
All these activities decreases the transmission and
distribution losses sufferred by the department besides
improving the voltage profile at the consumer's
premises.
During 2002-03 also, under the system improvement
scheme, installation of 3 Nos. of 11/0.4 KV
distribution sub-stations with a total capacity of 225
KVA, upgradation of 2 Nos. of 11/0.4 KV distribution
sub-stations with an additional capacity of 200 KVA,
erection of 1.2 Kms. of 11 KV line, erection of 0.9 Kms
of LT line and strengthening of 1.3 Kms of L.T. line
were completed.
|